| architecture - scope of services  programming/concept  design phase
 During this phase, the R2 Design Group, in conjunction with  your staff and key consultants, will create and/or refine the program and  generate concepts for the project.  As  part of this effort, we will review programming information, prepare site and  zoning analysis and prepare concept design alternatives for evaluation and  selection. Orientation Work  SessionWe will begin the program review process with an interactive  work session.  During this session, we  will meet with you to review and discuss project design goals, parameters and  general project requirements.  The  session will also include identification of all programming information that  has been prepared to date, as well as technical contacts, project budget review  and review of the project schedule.
 Site / Zoning /  Code AnalysisThe objective of this phase is to determine and document  factors that will impact the design of the project.  We will prepare analysis diagrams and other  material as required to document these factors.   Issues to consider are:
 
               Zoning;Traffic       – pedestrian, transit and vehicular;Adjacent       uses;Site       focal points;Orientation       and views;Public       space;Topography;Miscellaneous       opportunities and constraints; andBuilding       Code and construction types. Conceptual SchemesThe objective of this effort is to evaluate, in conjunction  with you and the project team, the site constraints and opportunities to allow  for maximum building potential and efficiency and to measure the site’s ability  to meet your requirements.  Up to three  (3) schemes will be evaluated during this phase.  The schemes will address the issues outlined  above.
 ConsultantsParallel with development of the conceptual schemes, the  design consultants and engineers will provide input as required to resolve  issues identified by the design team.
 Concept Design  PresentationThe R2 Design Group will make a formal presentation of the  concept design to you.  The presentation  will be a comprehensive review of site planning, programming, and building  concept design, structural, MEP and specialty consultant design.
 
 
 
 schematic  design phase
 Based on the your written comments and/or written approval  of the conceptual design documents, the R2 Design Group will prepare schematic  design documents consisting of drawings and other documents illustrating the  following: 
               Horizontal/vertical       dimensions and geometry of the various program elements;Material       strategy and selection;Pedestrian       and vehicular circulation,Structural       grids;Major       mechanical, electrical and plumbing space requirements; andStreetscape       and public spaces. ConsultantsConsultants will prepare studies and options and  recommendations, for approval during this phase.
 Schematic Design  DocumentsThe R2 Design Group and its consultants will prepare  schematic design documents that describe the design concepts.  The final schematic design phase submittal  documents will include the following:
 
               Civil
                 Site plan, including contours, easements,  boundary, building footprints and parking.Existing utilitiesSite lighting; andProposed utility improvements. 
               Structural
                 Proposed structural grid and system; andIdentify major member sizes. 
               Architecture
                 Floor plans;Building sections;Typical elevations;Sketches and models as required to convey design  intent;Materials and finish selection;Updated program, if required. 
               Mechanical and Plumbing
                 Heating, ventilating and cooling load  calculations;Single-line drawings of any mechanical equipment  spaces, duct chases and pipe chases required to support the interior design  concept;Location of all major equipment in allocated  spaces; andPlumbing routing diagrams and schematic riser  diagrams. 
               Electrical
                 Lighting fixtures outlined in plan and roughly  scheduled, showing type and quantities of fixtures to be used;Additional electrical equipment, required to  support the interior design concept, roughly scheduled indicating size and  capacity. 
               
                 Preliminary one-line electrical distribution  diagrams with indications of final location of any additional panels and  transformers (if required); and Legend showing all symbols used on drawings. 
               Specialty Consultants
                 These consultants will prepare all necessary  schematic design drawings and specifications for the drawing package. Schematic Design  PresentationThe R2 Design Group will make a formal presentation of the  schematic design to you.  The  presentation will be a comprehensive review of site planning, programming, and  building design, structural, MEP and specialty consultant design based on  approved concept design phase.
 
 
 design  development phase
 Based on the approved schematic design phase, the project  will enter the final development stage of design.  Resolution of design elements and details,  fine tuning of planning, and final selections of all materials will be  completed during design development. Work Sessions and  Periodic MeetingsSimilar to schematic design, this work session will begin  with a review of the design development deliverables, schedule and assignments,  and is intended as a method of confirming and directing the work of this  phase.  We will meet, if necessary,  weekly with the project team.  The R2  Design Group believes that this is usually necessary at the beginning of this  phase and can go to every other week later in the phase.
 Final Code and  American with Disabilities (ADA)  AnalysisThe R2 Design Group will conduct a final code analysis for  compliance with all applicable codes and ADA  requirements in effect at the time of project documentation.
 ConsultantsConsultants will prepare final design recommendations in the  form of reports and drawings for review and approval.
 Design Development  DocumentsThe R2 Design Group and its consultants will prepare design  development documents incorporating the work of all disciplines.  These drawings and specifications will  represent the basic infrastructure of the project.  Elements such as exterior skin, building  cores, structural systems, partitions, doors, ceilings, lighting, power and  communications outlets, floor and wall finishes, major architectural elements  and consultants’ systems will be described in sufficient detail for accurate  cost estimating.  Consultant packages  will describe major systems components and design intent. The final schematic  design phase submittal documents will include the following:
 
               Civil
                 Site plan, including contours, easements,  boundary, building footprints and parking.Existing utilitiesNew utilities;New site grading;Storm water design;Sanitary waste design;Unique civil requirements; andOutline specification 
               Structural
                 Structural grid;Structural system;Lateral structural system;Major structural sizes;Special foundation requirements; andOutline specification 
               Architecture/Interiors
                 Floor plans;Key design sections through building;Exterior building elevations describing all  materials;Typical wall profiles describing desired system;Enlarged elevations at critical design areas;Identification of all fixed and loose equipment  and cabinetry to be installed;In-progress reflected ceiling plan;In-progress door schedule;In-progress finish schedule;Color and material boards;Updated program, if required; andOutline specification. 
               Mechanical and Plumbing
                 Heating, ventilating and cooling load  calculations including loads generated by equipment, computers, etc.;Additional mechanical equipment scheduled  indicating size and capacity;Ductwork and piping substantially located and  sized;Ceiling devices located;Plumbing routing diagrams and schematic riser  diagrams; andOutline specifications. 
               Electrical
                 Coordination of furniture, fixtures and  equipment data.Additional electrical equipment (distribution,  panels, transformers, etc.) dimensioned and drawn to scale into the space  allocated;Lighting, power, telecommunications, and  automation devices and receptacles shown in plan;Final light fixture schedule: andOutline specifications. 
               Specialty Consultants
                 These consultants will prepare all necessary  design development drawings and specifications for the drawing package. Design Development PresentationThe R2 Design Group will make a formal design development  presentation to you.  The presentation  will be a comprehensive review of the entire project and is the final  decision-making step in the design process.
 
 
 construction  documents phase
 Based on the approved design development phase, the project  will enter the construction document (CD) phase and is the final documentation  and coordination of the architecture, engineering and specialty consultants’  work.  These documents will be completed  and detailed to cover all work within the R2 Design Group and its consultant’s  scope.  The package will include all  field construction, architectural millwork, fabrication, doors, glass and  glazing, lighting, special features, materials, finishes, etc. Document CoordinationThe R2 Design Group will coordinate the construction  contract documents with those prepared by the consultant team.  After a multi-disciplinary review, we will  incorporate the revisions into a final set of documents that will be used for  bidding.
 Project ManualThe R2 Design Group will prepare the final project manual,  including General and Supplemental Conditions, all bidding and contracting  requirements and technical specifications in the Masterspec 33 division  format.  The specifications shall reflect  current construction practices.
 Construction Cost  ControlIf required, the R2 Design Group shall collaborate with you in  cost reduction decisions.  If acceptable,  additive or deductive alternates may be included in the bidding documents in an  effort to keep the project within budget.
 
 
 bidding/negotiation  phase
 During this phase, the R2 Design Group will assist you in  determining the most appropriate construction delivery method (i.e.  Construction Manager at risk, Construction Manager not at risk, General  Contractor, etc.). Clarifications and  AddendaThe R2 Design Group will prepare such clarifications and  addenda to the bidding documents as may be required.  This will include providing responses to  written questions from bidders.
 Pre-bid ConferenceThe R2 Design Group will conduct a Pre-bid Conference with  prospective bidders to review the project requirements.  We will provide knowledgeable  representatives, including representatives of our consultants, to participate  in this conference to explain and clarify the bidding documents.  If needed, a final addendum will be delivered  to bidders typically within five (5) calendar days before the bids are due.
 Evaluation of  Construction BidsThe R2 Design Group will receive the construction bids, if  requested by you, and evaluate the bids.   We will coordinate questions to bidders and assist in the selection  process.
 
 
 construction  administration phase Under basic services for the construction phase, the R2  Design Group will commence our services at the award of the contract for  construction and terminate our services at the issuance of the final  Certificate of Payment or thirty (30) days past substantial completion. Site VisitsThe R2 Design Group will visit the project construction site  periodically during construction to observe progress.  These visits will be timed to coincide with  the construction progress meeting with the contractor.  We will prepare field reports after each site  visit.
 Each of our consultants shall make periodic visits during  the course of work applicable to its discipline.  The engineering disciplines shall prepare and  submit a report on each visit, submitted via the R2 Design Group typically within  three (3) working days of the visit. Submittal LogsDuring this period, the R2 Design Group and their  consultants will assist the contractor in the preparation of a list of expected  submittals, including tests required, and operation and maintenance (O&M)  information.  This list shall be  organized according to the applicable specification section.  This list shall be the basis for the  submittal logs for this project.
 Shop Drawing and  Submittal ReviewThe R2 Design Group will review submittals and shop drawings  as required in the contract documents.   The review and return of submittals shall be accomplished by the R2  Design Group, and their consultants, on or before fourteen (14) calendar days  from date of receipt.
 Construction  DirectivesThe R2 Design Group will use standard AIA forms and  procedures for the preparation of construction directives.  These include Architect’s Supplemental  Instructions, Request for Proposal and Change Orders.
 Punch List ReviewUpon written declaration from the contractor that the work  is substantially complete, the R2 Design Group will review the construction and  prepare a punchlist of the contractor’s work which is not in conformance with  the construction contract documents.   Additional items will be added to the punch list as required.
 Progress Payment  Request ReviewsIf required, the R2 Design Group will assist you in review,  approval and forwarding of the contractor and vendor applications for payment  and lien releases.
     |